{"id":4703,"date":"2026-11-18T08:02:43","date_gmt":"2026-11-18T07:02:43","guid":{"rendered":"https:\/\/energianucleare.eu\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/"},"modified":"2026-11-18T08:02:43","modified_gmt":"2026-11-18T07:02:43","slug":"north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s","status":"publish","type":"post","link":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/","title":{"rendered":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s"},"content":{"rendered":"<p>The North Carolina Utilities Commission on Monday approved <strong>Duke Energy&#8217;s 2025 Carolinas Resource Plan<\/strong> and authorized the company to continue developing new nuclear, using either small modular reactors (SMRs) or large light-water reactors. The plan looks out to 2034 and serves 4.8 million customers across North Carolina and South Carolina.<\/p>\n<p>On the nuclear front, the commission extended through 2028 the authorization to spend up to <strong>$440 million<\/strong> on development activities. The goal is to keep both options open. Duke&#8217;s plan calls for 1,117 MW of nuclear capacity by 2037, split between SMRs and large reactors, compared with the 600 MW of SMRs alone in the 2023 plan. The reference sites are Belews Creek in North Carolina for SMRs and W.S. Lee in South Carolina for large reactors.<\/p>\n<p>Duke Energy may also prepare and submit to the Nuclear Regulatory Commission the amendments for <strong>two AP1000 units at W.S. Lee<\/strong>, in Cherokee County. The commission also approved revising the combined license for two AP1000s at the Shearon Harris site in Wake County, keeping the existing licenses up to date and usable.<\/p>\n<p>The commission opened a dedicated nuclear docket, with quarterly progress updates. A technical conference is planned for 2027 on technology, costs, financing and customer protections. Those assessments precede any decision to build a new plant, which has not yet been made.<\/p>\n<p>The backdrop is sharply rising electricity demand. According to S&#038;P Global, Duke expects growth to more than double the 2023 plan&#8217;s forecast, driven by new industrial developments and digital infrastructure. The plan also factors in regulatory changes at the state and federal levels, with broader support measures for small and large nuclear. The company estimates that customer costs over the next ten years will fall by nearly half compared with the plan approved in 2024.<\/p>\n<p>Nuclear sits alongside other sources. The order approves an additional 2,300 MW of solar, for a total of 8,100 MW by 2034, and 2,700 MW of storage, for 5,400 MW overall. It also includes 2,720 MW of combined-cycle gas plants and 1,111 MW of combustion turbines beyond what has already been authorized.<\/p>\n<p>For the industry, the decision has practical value. Duke keeps NRC licensing work and technology selection moving, with an in-service horizon set at 2037. The key milestone will be the 2027 technical conference, which will shape the choice between the flexibility of SMRs and the output of AP1000s.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>The North Carolina Utilities Commission has approved Duke Energy&#8217;s 2025 Carolinas Resource Plan and authorized continued nuclear development, spanning SMRs and large reactors. It also cleared the way for NRC license amendments for two AP1000 units at W.S. Lee and Shearon Harris.<\/p>\n","protected":false},"author":25,"featured_media":4700,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[],"tags":[],"class_list":["post-4703","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare<\/title>\n<meta name=\"description\" content=\"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare\" \/>\n<meta property=\"og:description\" content=\"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/\" \/>\n<meta property=\"og:site_name\" content=\"Energia nucleare\" \/>\n<meta property=\"article:published_time\" content=\"2026-11-18T07:02:43+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1536\" \/>\n\t<meta property=\"og:image:height\" content=\"1024\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Redazione Energia Nucleare\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Redazione Energia Nucleare\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/\"},\"author\":{\"name\":\"Redazione Energia Nucleare\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/#\\\/schema\\\/person\\\/2c3f466ad139658dfa60c575cf287fb7\"},\"headline\":\"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s\",\"datePublished\":\"2026-11-18T07:02:43+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/\"},\"wordCount\":395,\"commentCount\":0,\"image\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/energianucleare.eu\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/nucleare-centrale-torri-vapore-fiume-1.jpg\",\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/\",\"url\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/\",\"name\":\"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/energianucleare.eu\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/nucleare-centrale-torri-vapore-fiume-1.jpg\",\"datePublished\":\"2026-11-18T07:02:43+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/#\\\/schema\\\/person\\\/2c3f466ad139658dfa60c575cf287fb7\"},\"description\":\"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#primaryimage\",\"url\":\"https:\\\/\\\/energianucleare.eu\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/nucleare-centrale-torri-vapore-fiume-1.jpg\",\"contentUrl\":\"https:\\\/\\\/energianucleare.eu\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/nucleare-centrale-torri-vapore-fiume-1.jpg\",\"width\":1536,\"height\":1024,\"caption\":\"Centrale nucleare con due alte torri di raffreddamento che emettono vapore accanto a un edificio a cupola e a un fiume\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/\",\"name\":\"Energia nucleare\",\"description\":\"Notizie sul nucleare\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/#\\\/schema\\\/person\\\/2c3f466ad139658dfa60c575cf287fb7\",\"name\":\"Redazione Energia Nucleare\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g\",\"caption\":\"Redazione Energia Nucleare\"},\"url\":\"https:\\\/\\\/energianucleare.eu\\\/en\\\/author\\\/redazione\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare","description":"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/","og_locale":"en_US","og_type":"article","og_title":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare","og_description":"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.","og_url":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/","og_site_name":"Energia nucleare","article_published_time":"2026-11-18T07:02:43+00:00","og_image":[{"width":1536,"height":1024,"url":"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg","type":"image\/jpeg"}],"author":"Redazione Energia Nucleare","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Redazione Energia Nucleare","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#article","isPartOf":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/"},"author":{"name":"Redazione Energia Nucleare","@id":"https:\/\/energianucleare.eu\/en\/#\/schema\/person\/2c3f466ad139658dfa60c575cf287fb7"},"headline":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s","datePublished":"2026-11-18T07:02:43+00:00","mainEntityOfPage":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/"},"wordCount":395,"commentCount":0,"image":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#primaryimage"},"thumbnailUrl":"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg","inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/","url":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/","name":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s - Energia nucleare","isPartOf":{"@id":"https:\/\/energianucleare.eu\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#primaryimage"},"image":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#primaryimage"},"thumbnailUrl":"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg","datePublished":"2026-11-18T07:02:43+00:00","author":{"@id":"https:\/\/energianucleare.eu\/en\/#\/schema\/person\/2c3f466ad139658dfa60c575cf287fb7"},"description":"Duke Energy wins North Carolina approval: nuclear development with SMRs or AP1000s, up to $440 million through 2028.","breadcrumb":{"@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#primaryimage","url":"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg","contentUrl":"https:\/\/energianucleare.eu\/wp-content\/uploads\/2026\/11\/nucleare-centrale-torri-vapore-fiume-1.jpg","width":1536,"height":1024,"caption":"Centrale nucleare con due alte torri di raffreddamento che emettono vapore accanto a un edificio a cupola e a un fiume"},{"@type":"BreadcrumbList","@id":"https:\/\/energianucleare.eu\/en\/north-carolina-regulator-approves-duke-energy-plan-with-smrs-and-two-ap1000s\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/energianucleare.eu\/en\/"},{"@type":"ListItem","position":2,"name":"North Carolina Regulator Approves Duke Energy Plan With SMRs and Two AP1000s"}]},{"@type":"WebSite","@id":"https:\/\/energianucleare.eu\/en\/#website","url":"https:\/\/energianucleare.eu\/en\/","name":"Energia nucleare","description":"Notizie sul nucleare","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/energianucleare.eu\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/energianucleare.eu\/en\/#\/schema\/person\/2c3f466ad139658dfa60c575cf287fb7","name":"Redazione Energia Nucleare","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/f7573bf636adfceb968c63d469c0889af0a78eb4935f321c17f76df121e056a6?s=96&d=mm&r=g","caption":"Redazione Energia Nucleare"},"url":"https:\/\/energianucleare.eu\/en\/author\/redazione\/"}]}},"_links":{"self":[{"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/posts\/4703","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/users\/25"}],"replies":[{"embeddable":true,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/comments?post=4703"}],"version-history":[{"count":0,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/posts\/4703\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/media\/4700"}],"wp:attachment":[{"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/media?parent=4703"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/categories?post=4703"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/energianucleare.eu\/en\/wp-json\/wp\/v2\/tags?post=4703"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}