Denison Mines Reaches 24% Completion at Phoenix Uranium Mine

Denison Mines has completed 24% of construction at the Phoenix uranium mine in Saskatchewan after its first quarter of full-scale work. First production is expected in mid-2028.

Denison Mines Reaches 24% Completion at Phoenix Uranium Mine

Denison Mines has reached 24% overall completion at the Phoenix uranium mine in Saskatchewan, following its first quarter of full-scale construction. The figure comes from the company’s third-quarter 2026 results, released on November 4.

The project entered its main construction phase on July 28, when the company announced the end of site preparation activities. Phoenix is located on the Wheeler River property in the Athabasca Basin. The integrated Denison-Wood management team had already arrived on site in early March. Wood Canada won the construction management contract through a competitive tender and is overseeing procurement, project controls and construction of the entire processing plant.

Phoenix will use the in-situ recovery technique. A special solution is injected underground to dissolve the uranium contained in the rock, and the resulting liquid is then pumped to the surface and processed. No open-pit mining or conventional underground tunnels are required. According to the feasibility study, the Wheeler River deposits can compete with the lowest-cost mines in the world.

The permitting process took years. Applications began in 2019. The Province of Saskatchewan approved the environmental assessment in July 2025. In February 2026, the Canadian Nuclear Safety Commission gave final approval and issued the construction licence. Phoenix is the first Canadian uranium mine to receive federal approval in more than twenty years. On February 24, the board of directors made the final investment decision. In early July, the Peter Ballantyne Cree Nation withdrew its legal challenge and confirmed its support for the project.

Initial capital expenditure is estimated at around $600 million, a figure updated in January 2026 and adopted as the control budget. Construction will take about two years, with first production expected in mid-2028. Financing was secured before work began. CEO David Cates said that the combination of physical uranium holdings, active production at McClean Lake and future mines has been well received by some of the world’s largest nuclear utilities.

For power producers, the impact is tangible. Denison is among the few global suppliers able to add a significant volume of new uranium before the end of the decade. Reactor operators in Europe and Italy are looking for reliable fuel sources outside geopolitical flashpoints, and Canada is a natural candidate.

If the schedule holds, Phoenix will come online just as many countries are planning new reactors and SMRs. Wheeler River’s second deposit, Gryphon, is the subject of a separate pre-feasibility study and could extend Denison’s presence in the Canadian uranium market.