The European Investment Bank (EIB) has signed a €400 million agreement with Nuclearelectrica for the refurbishment of Unit 1 at Romania’s Cernavodă nuclear power plant. The loan is the first half of an €800 million package and aims to extend the reactor’s operating life by 30 years.
The funds will be used to replace components and upgrade the unit’s systems. The EIB’s board of directors approved the full amount in July 2026. The contract was signed on Monday, following approval from the company’s shareholders, who gave a mandate to contract the entire €800 million in support. The second €400 million tranche is expected in 2027.
The refurbishment project is worth about €3.1 billion in total. EIB financing therefore covers a significant share of it, while the remainder comes from other sources, including state guarantees and additional forms of support. According to EIB Vice-President Ioannis Tsakiris, the refurbishment will help ensure stable, low-cost, low-emission electricity for millions of consumers. Nuclearelectrica CEO Mihai Gioara calls it a strategic investment in the country’s energy security.
Unit 1 entered service in 1996 and has an electrical capacity of about 700 MW. It is a CANDU reactor, a heavy-water technology of Canadian origin. The Cernavodă plant has two units of this type, among the most efficient in the world by capacity factor out of more than 400 operating reactors. Together they cover about one fifth of Romania’s electricity demand.
The refurbishment outage is scheduled between 2027 and 2030, in line with the end of the unit’s original design life. Preparation has been organized in phases, and the final one includes shutting down the unit and carrying out the actual works. The refurbishment is being conducted in compliance with nuclear regulatory requirements. The reactor will return to producing low-emission electricity for another three decades, using existing infrastructure and at a cost per megawatt lower than that of a new plant.
For Romania, the decision carries weight beyond national borders. While Unit 1 is offline, Unit 2 will continue to supply power to the grid. When the reactor returns to service, Bucharest will have a guaranteed nuclear base through the 2060s. The model is replicable for other European CANDU reactors approaching the same threshold.