Nexus Uranium Advances Chord Project in South Dakota After Appeals Court Ruling

Nexus Uranium has updated the market on permitting for its Chord project in South Dakota. The Eighth Circuit upheld the dismissal of an action tied to the exploration permit hearing, while Washington continues to back domestic uranium.

Nexus Uranium Advances Chord Project in South Dakota After Appeals Court Ruling

Nexus Uranium has issued an update on the Chord project in Fall River County, South Dakota. On October 26, 2026, the Eighth Circuit Court of Appeals affirmed the dismissal of an action filed in federal district court in connection with the hearing on the exploration permit.

Chord is following two separate permitting tracks. The first is at the state level: application EXNI 453 before the South Dakota Board of Minerals and Environment, the body reviewing the exploration permit for state-owned land. The second is federal and covers National Forest System lands, where the process with the Forest Service and the Permitting Council remains ongoing. The company says it is working with the agencies responsible for each process.

The project spans roughly 3,640 contiguous acres in the historic Edgemont uranium district in the Black Hills region. It lies about three miles southeast of Dewey Burdock, the in-situ recovery project owned by enCore Energy. Dewey Burdock entered the federal FAST-41 program in August 2025, which assigns each project a federal point of contact, a coordinated permitting timetable and tracking on a public dashboard. Nexus submitted its own request for FAST-41 access for Chord in January 2026.

The US policy backdrop remains supportive. In its update, Nexus notes that since uranium was designated a critical mineral, the US government has continued to move in support of domestic production. The House passed, by a vote of 394 to 3, a bill on uranium preparation for nuclear fuel. It does not cover mining, so Chord will still need to complete its own permits, but it points to bipartisan consensus on the fuel supply chain.

For Nexus, Chord is the flagship project. Its South Dakota portfolio also includes Wolf Canyon, Deadhorse and RC, totaling about 6,380 acres. Other activities are advancing in parallel: South Pass in Wyoming, and an option on a single target within the Arizona Strip project, under a deal fully funded by the partner with no capital commitment or dilution for Nexus.

Demand for American uranium is growing with the nuclear revival, from existing reactors to SMRs. If Chord secures its state and federal permits, the company will be able to move on to exploration drilling and test the resource in a district where in-situ recovery developers have already paved the way on permitting.