The US Nuclear Regulatory Commission has approved a construction permit for four X-energy Xe-100 modular reactors at Dow’s Seadrift site on the Texas Gulf Coast. The project, called Long Mott Generating Station, totals 320 MWe. According to industry press reports, it is the first time the NRC has issued a permit of this kind for a reactor at an industrial site.
The Xe-100 is an 80 MWe, 200 MWt high-temperature gas-cooled reactor fueled with TRISO-X fuel. For X-energy, it is the first construction permit for a reactor of this family in the United States. The NRC chairman described it as the first issued in more than half a century for a high-temperature gas-cooled reactor. The commission’s documentation finds that the project can be safely sited and built inside an operating plant.
The permit came earlier than expected. Dow and X-energy filed the application on March 31, 2025, and the review could have taken up to 30 months. The NRC completed its environmental review in less than a year, helped by pre-licensing work that began in 2018. X-energy CEO Clay Sell credited the speed to the commission’s efficiency and to the reforms passed by Congress over the past six years. The path began in 2020, when the Department of Energy selected X-energy for the Advanced Reactor Demonstration Program.
The plant will serve Dow’s chemical facility. It is expected to supply electricity and industrial steam and to replace nearby energy assets approaching the end of their life. The Xe-100 units at Seadrift are expected to power the site for 60 years. The permit sets July 1, 2033 as the earliest completion date, while X-energy refers to the early 2030s.
The approval does not settle the industrial question. Dow plans to evaluate a preliminary investment decision in 2027, and actual construction will begin only after the final decision. Edward Stones, Dow’s head of energy and climate, outlined three criteria: competitiveness, execution capability and capital sustainability. Costs have not been disclosed. In the meantime, the permit allows the design to be refined, the supply chain for long-lead components to be developed and the operating license application to be prepared.
For X-energy, the result matters well beyond Texas. The company reports a commercial pipeline of more than 11 GW, equivalent to 144 Xe-100 reactors. Projects include the twelve modules funded by Amazon in Indiana and up to 6 GW to be developed with UK-based Centrica. If Seadrift reaches operation, American heavy industry will have a concrete reference for powering plants with nuclear heat and electricity.