FluxPoint Energy has completed a seed funding round to develop a uranium conversion facility in the United States. Market and technical feasibility studies are finished, and the company is aiming to begin commercial production in 2030-2031. It would be the first plant of its kind built in the country in nearly 70 years.
The funds will go toward three concrete activities: detailed front-end engineering design (FEED), permitting, and expansion of the technical team. The press release, issued on November 10, 2026 via PR Newswire and later corrected by the company, describes the round as the first step toward construction and toward building the organization needed for the next phases. The amount raised was not disclosed.
Conversion is the stage that turns uranium oxide concentrate, known as yellowcake, into uranium hexafluoride (UF6). The compound is the feedstock for enrichment, which in turn precedes reactor fuel fabrication. Without this step, mined uranium cannot fuel a power plant. In the process, solid oxide reacts with fluorine gas to produce UF6, which is then cooled into solid form for transport to enrichment facilities.
The United States currently has just one commercial conversion plant: Metropolis Works in Illinois, built in 1958. The rest of the capacity is in the hands of foreign operators. FluxPoint, headquartered in Houston and McLean, Virginia, made its official debut at CERAWeek in March 2026. It is led by Mike Chilton, who has more than thirty years of experience in nuclear fuel and a background as operations manager at the Sequoyah Fuels plant, which was built specifically to convert yellowcake into UF6.
The company is not alone. Uranium Energy Corp is developing a competing facility through its subsidiary United States Uranium Refining & Conversion Corp, which on March 18, 2026 received a docket number from the Nuclear Regulatory Commission for its licensing proceeding. UEC’s project envisions 10,000 tonnes of UF6 per year, more than half of the estimated domestic demand of roughly 18,000 tonnes.
The backdrop is the expansion of US nuclear power. Utilities and developers are planning new generation and restarts, and fuel availability is increasingly cited as the constraint to be resolved. Mining, conversion, enrichment and fabrication all need to grow together, and conversion is the link with the fewest domestic alternatives.
The schedule remains the test: if FluxPoint and UEC meet their licensing milestones, the United States could have three domestic UF6 suppliers by 2031 instead of one.